Budgeted cost is $150000. PV = 110, EV = 90, and AC = 80 at week 30. Calculate schedule, cost and time variances, as well

Budgeted cost is $150000. PV = 110, EV = 90, and AC = 80 at week 30. Calculate schedule, cost and time variances, as well as schedule and cost performance indices for Week 30. Then use this information to comment on the project progress at Week 30 (status date). Based on the performance at Week 30, estimate the final project cost (EAC). Will the final project cost be higher or lower than the budgeted cost, and by how much? Also estimate the revised project completion date. Will the project complete sooner or later than the planned completion date, and by how many weeks

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Management Science

Authors: Bernard W. Taylor

13th Edition

0134730666, 978-0134730660

More Books

Students also viewed these General Management questions

Question

Be straight in the back without blowing out the chest

Answered: 1 week ago

Question

Wear as little as possible

Answered: 1 week ago

Question

Be relaxed at the hips

Answered: 1 week ago