Buenaflor Industries Research and Development Department is tasked to come up with an oral anti-viral pill. Presented below are the list of activities, precedence relations,
Buenaflor Industries Research and Development Department is tasked to come up with an oral anti-viral pill. Presented below are the list of activities, precedence relations, and duration for the project.
Draw the appropriate AON PERT diagram.
What is the critical path? Encode your answer in this manner: ABCD. *
What is the total project completion time? Encode your answer in this manner: 2 DAYS. *
What is the early finish of activity D? Encode your answer in this manner: 2 DAYS. *
What is the early finish of activity H? Encode your answer in this manner: 2 DAYS.
What is the late start of activity C? Encode your answer in this manner: 2 DAYS.
What is the late start of activity I? Encode your answer in this manner: 2 DAYS.
Compute for the slack time of activity F? Encode your answer in this manner: 2 DAYS.
ACTIVITY NAME A B C DEFGH G I J K ACTIVITY DESCRIPTION Initial Idea Testing if the ideas work Developing Reagents Testing to measure success Clinical Trial - Phase 1 Clinical Trial - Phase 2 Clinical Trial - Phase 3 Clinical Trial - Phase 4 Clinical Trial - Phase 5 Clinical Trial - Phase 6 Product Launching PREDECESSOR NONE A B A, C D E C D, E, G, J C G, H F, H, J TIME IN MONTHS 5 4 2685 5 4 13 2 1 6
Step by Step Solution
3.39 Rating (158 Votes )
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started