Buffalo Company manufactures toy trucks. Orders for 7,300 trucks were received during March, with deliveries scheduled evenly throughout the month of April. Trucks are produced

Buffalo Company manufactures toy trucks. Orders for 7,300 trucks were received during March, with deliveries scheduled evenly throughout the month of April. Trucks are produced simultaneously in 10 manufacturing cells. Time available for production in each cell is 7 hours per day for 21 days during March.

Calculate the takt time. (Round answer to 1 decimal place, e.g. 15.2.)
Takt time

minutes per truck

LINK TO TEXT

At the end of the first hour of a days production, one cell had completed 4 good trucks, including one truck that was reworked. Calculate the day-by-the-hour results and the variance. (Round answers to 1 decimal place, e.g. 15.2. Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)
Day-by-the-hour

trucks per hour
Variance

trucks

LINK TO TEXT

At the end of the first hour of a days production, one cell had completed 4 good trucks, including one truck that was reworked. Calculate the first time through (FTT) rate. (Round answer to 2 decimal places, e.g. 15.26%.)
First time through rate

%

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Microeconomics Theory And Applications

Authors: Edgar K. Browning, Mark A. Zupan

13th Edition

1119368928, 9781119368922

More Books

Students also viewed these Accounting questions

Question

Name three types of seals applied to rotating shafts.

Answered: 1 week ago

Question

1. Administrative routines, such as taking attendance

Answered: 1 week ago