Question
Building a backyard swimming pool consists of nine major activities. The activities, their immediate predecessors, and times are shown. (I have calculated for you the
Building a backyard swimming pool consists of nine major activities. The activities, their immediate predecessors, and times are shown. (I have calculated for you the expected times and the variances.)
Activity Immediate Optimistic Most Pessimistic Expected Var.
Predecessor Probable Times
A - 3 5 7 5 .44
B - 2 4 6 4 .44
C A,B 5 6 7 6 .11
D A,B 8 9 10 9 .11
E B 2 4 6 4 .44
F C 1 2 3 2 .11
G D 5 7 9 7 .44
H D,F 5 8 11 8 1.00
I E,G,H 3 4 5 4 .11
You do not have to submit the diagram. Show work on all questions. What are the activities on the critical path?
What is the probability that the project can be completed in 28 days?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started