BUILDING COMPANY provided the following information about one of it's construction contracts (CONTRACT XY): Cost incurred to date: $500,000 Cost to complete: $2,500,000 Contract price
BUILDING COMPANY provided the following information about one of it's construction contracts (CONTRACT XY):
Cost incurred to date: $500,000
Cost to complete: $2,500,000
Contract price = Total Cost Plus $1,000,000
Amount paid to date by client: $100,000
How much revenue should BUILDING COMPANY recognize on CONTRACT XY?
Select one:
a. $500,000
b. $250,000
c. $800,000
d. $1,000,000
e. None of these answers
How much PROFIT/LOSS should BUILDING COMPANY recognize on CONTRACT XY?
Select one:
a. None of these answers
b. PROFIT OF $800,000
c. PROFIT OF $1,000,000
d. PROFIT OF $500,000
e. PROFIT OF $250,000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started