Business Move Your business has outgrown its current location, so you have sold your current space and have leased a larger building at a new

Business Move
Your business has outgrown its current location, so you have sold your current space and have leased a larger building at a new location in downtown Kitchener, Ontario. Since your daily work activities leave you little time to prepare for the move, you have decided to create a moving plan in Project to ensure steps don't get missed along the way. Your assistant has created the initial task list for you in Project. You now need to develop a more detailed project plan by creating a Work Breakdown Structure and assigning resources to individual tasks. You will also export your project to Excel and copy the project's tasks to a Word document.
a. Browse to the location where you are storing your files and open Lab1.mpp. Save the file as Practical_Lab1_LastFirst.mpp.
b. Set the start date of your project to 7/1/24.
c. Set new project tasks to Auto Scheduled.
d. Change the project's calendar to the work times of 1:00 PM to 4:00 PM MondayFriday.
e. Add a calendar exception for July 45,2024. Name the exception Independence Day.
f. Create a Work Breakdown Structure by doing the following:
Indent Tasks 25 to make them subtasks of Task 1.
Indent Tasks 710 to make them subtasks of Task 6.
Indent Tasks 1215 to make them subtasks of Task 11.
Indent Tasks 1720 to make them subtasks of Task 16.
Indent Tasks 2226 to make them subtasks of Task 21.
Indent Tasks 2831 to make them subtasks of Task 27.
Indent Tasks 3338 to make them subtasks of Task 32.
g. Change the duration of Tasks 1213 to 1ew.
h. On the Resource Sheet, add the following resources:
Resource Name Type Initials
Your Name Work YN
Suzane Smith Work SS
Joseph Schalow Work JS
Moving Company Work MC
i. Assign resources to the tasks as follows:
Assign Suzane Smith to Tasks 25.
Assign Suzane Smith and Your Name to Tasks 1213.
Assign Joseph Schalow to Tasks 1720 and Tasks 2831.
Assign Your Name to Tasks 710, Tasks 1415, Tasks 2226, and Tasks 3538.
Assign Moving Company to Tasks 3334.
j. To remove Your Name overallocations on Tasks 2325, change the Predecessor of Task 25 to 24
k. Select Task 12. Open the Split View and select the Work view. Change the hours assigned to Your Name and Suzane Smith on Task 12 to 0. Select Task 13. In the Split View, change the hours assigned to Your Name and Suzane Smith on Task 13 to 0. Remove the Split View.
l. The move-in day is scheduled for September 9,2024. Therefore, you must start packing on September 4,2024. On Task 33, set a Must Start On constraint. Set the Constraint date to 9/4/2024. When the Planning Wizard dialog box appears, select Continue. A Must Start On constraint will be set.
m. On Task 34, set a Must Start On constraint. Set a Constraint date of 9/9/24. Change the Calendar on this task only to the 24 hours calendar. When the Planning Wizard dialog box appears, select Continue. A Must Start On constraint will be set.
n. Add the Task Note Move in must occur on this day only. to Task 34.
o. Increase the height of Row 34 so all the indicators are shown.
p. Hide the Task Mode column.
q. Insert a column to the left of Task Name titled WBS. Set the WBS-Define Code to Uppercase Letters, Lowercase Letters, and then Numbers (Level 1, Level 2, and Level 3, respectively). Adjust the column width as needed.
r. Wrap the text of the task names in the Task Name column if necessary to show the entire task names.
s. Spell check the entire project.
t. Display the Timeline. Add all Summary Tasks to the Timeline.
u. Add a Project Summary Task. Name the task Business Move.
v. Add your name as a left footer in the Gantt Chart view and Network Diagram view.
w. Export the project as an Excel Project Template to a location where you store your files. Save the workbook as Lab1_Solution1_LastFirst.
x. Copy the Entry table into a blank Word document, save the document as Lab1_Solution2_LastFirst and then close Word.
y. Exit Project 2019/2021, and then submit your files to eConestoga Submission folder.
give a step by step guide for someone who has never used microsoft project on how to achive this task on microsoft project

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Database Processing

Authors: David Kroenke

11th Edition

0132302675, 9780132302678

More Books

Students also viewed these Databases questions