By examining the __________ for the project, the project, the project manager can determine Which activities must be completed sequentially and Which can be completed
By examining the __________ for the project, the project, the project manager can determine Which activities must be completed sequentially and Which can be completed concurrently with other activities as well as Wich activities must precede Which other activities.
WBS
Critical Path
performance indicators
durations