By using PERT draw the network diagram and determine ,o2, ES, EF, LS, LF, and C.P for the following Table. What is the probability

By using PERT draw the network diagram and determine ,o2, ES, EF, LS, LF, and C.P for the following Table.

By using PERT draw the network diagram and determine ,o2, ES, EF, LS, LF, and C.P for the following Table. What is the probability of completing the project on or before 49 weeks? If the probability of completing the project is 0.71, find the expected project completion time? Activities To 1-2 1-3 1-4 2-6 3-4 3-5 12 3-7 6 4-6 9 5-6 4 5-7 6-8 08 7-8 10 12 4 0 650 Tm 13 11 15 7 0 18 12 12 6 0 8 9 12 Tp 22 20 18 16 0 36 18 27 8 0 11 33 By using PERT draw the network diagram and determine ,o2, ES, EF, LS, LF, and C.P for the following Table. What is the probability of completing the project on or before 49 weeks? If the probability of completing the project is 0.71, find the expected project completion time? Activities To 1-2 1-3 1-4 2-6 3-4 3-5 12 3-7 6 4-6 9 5-6 4 5-7 6-8 08 7-8 10 12 4 0 650 Tm 13 11 15 7 0 18 12 12 6 0 8 9 12 Tp 22 20 18 16 0 36 18 27 8 0 11 33

Step by Step Solution

3.63 Rating (150 Votes )

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Analysis For Management

Authors: Barry Render, Ralph M., Jr. Stair, Michael E. Hanna, Trevor S. Hale

13th Edition

134543165, 978-0134543161

More Books

Students also viewed these Computer Network questions

Question

Solve each equation. x 3 - 6x 2 = -8x

Answered: 1 week ago