C: CASE STUDY HSH Sdn Bhd produces handmade shoes for children based in Melaka. There are three workers who are employed to run the production.
C: CASE STUDY
HSH Sdn Bhd produces handmade shoes for children based in Melaka. There are three workers who are employed to run the production. It is the companys policy to set the normal working hours at 8 hours a day, operating 5 days in a week. Provided below is the information gathered from the weekly time sheet for Week 3 April 2021.
Employees |
| Weekly hours worked | Output produced (in pairs) | Rejected output (in pairs) | |||
Monday | Tuesday | Wednesday | Thursday | Friday |
|
| |
Monica | 10 | 11 | 10 | 9 | 8 | 215 | 4 |
Rachel | 11 | 10 | 9 | 11 | 11 | 227 | 3 |
Joey | 8 | 8 | 8 | 8 | 8 | 156 | 8 |
Monica and Rachel are skilled workers who are paid based on an hourly rate which is RM9.00 per hour. Skilled workers are entitled for overtime payment. The company decides an overtime rate of 1.5 times of the normal rate. Meanwhile, Joey is a semi-skilled worker who is paid based on differential piecework scheme with a weekly minimum guaranteed wage of RM400. The differential piecework pay scheme is as follows: Weekly Production Level Rate of pay 1 50 units RM2.00 per pair 51 100 units RM2.50 per pair 101 150 units RM3.00 per pair 151 and above RM3.50 per pair
Required:
Calculate the followings for Week 3 April 2021:
1. The normal working hours for the company. (1 mark)
2. Actual hours worked by Monica. (1 mark)
3. Overtime hours worked by Monica. (1 mark)
4. The basic pay on normal working hours for Monica. (1 mark)
5. The basic pay on overtime hours for Monica. (1 mark)
6. The premium pay on overtime hours for Monica. (1 mark)
7. The total gross wages for Monica. (1 mark)
8. Actual hours worked by Rachel. (1 mark)
9. Overtime hours worked by Rachel. (1 mark)
10. The basic pay on normal working hours for Rachel. (1 mark)
11. The basic pay on overtime hours for Rachel. (1 mark)
12. The premium pay on overtime hours for Monica. (1 mark)
13. The total gross wages for Rachel. (1 mark)
14. Total output produced by Joey. (1 mark)
15. The rejected output by Joey. (1 mark)
16. The number of good outputs produced by Joey. (1 mark)
17. The calculated gross wages for Joey using the differential piecework scheme. (1 mark)
18. The gross wages that will be paid to Joey. (1 mark)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started