C T= 3 A T= 2 B T= 1 D T=2 E T= 4 F T= 3 G T= 2 The network diagram of
C T= 3 A T= 2 B T= 1 D T=2 E T= 4 F T= 3 G T= 2 The network diagram of a project along with the activity durations (T) are given in the figure. In this project what is the slack time for activity C? (Only enter the number, do not try to enter the unit)@orsdemir. Copyrighted content. Cannot be posted.