Question
C&A Dairy makes two flavors of ice creamchocolate and vanilla. Each gallon is produced and shipped in discrete containers. The demand for the ice cream
C&A Dairy makes two flavors of ice creamchocolate and vanilla. Each gallon is produced and shipped in discrete containers. The demand for the ice cream (in gallons) is given as follow:
Day | Chocolate | Vanilla |
---|---|---|
1 | 30 | 40 |
2 | 25 | 20 |
3 | 50 | 60 |
4 | 35 | 35 |
5 | 60 | 45 |
C&A operates two shifts per day, 8 hours per shift, and 5 days a week. What is the takt time and how should C&A schedule the production of its ice cream to level demand?
C&A Dairy makes two flavors of ice creamchocolate and vanilla. Each gallon is produced and shipped in discrete containers. The demand for the ice cream (in gallons) is given as follow:
Day | Chocolate | Vanilla |
---|---|---|
1 | 30 | 40 |
2 | 25 | 20 |
3 | 50 | 60 |
4 | 35 | 35 |
5 | 60 | 45 |
C&A operates two shifts per day, 8 hours per shift, and 5 days a week. What is the takt time and how should C&A schedule the production of its ice cream to level demand?
12 minutes per gallon, alternate between 1 unit of chocolate and 2 units of vanilla
12 minutes per gallon, alternate between 2 units of chocolate and 1 unit of vanilla
12 minutes per gallon, alternate between 1 unit of chocolate and 1 unit of vanilla
4 minutes per gallon, alternate between 1 unit of chocolate and 1 unit of vanilla
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started