Cabinet Makers set the following standard cost per unit for 2019. Fixed overhead (4 machine hours at
Fantastic news! We've Found the answer you've been seeking!
Question:
Cabinet Makers set the following standard cost per unit for 2019. Fixed overhead (4 machine hours at $10.00) $40 Variable overhead (4 machine hours at $8) $32 The standards were sat based on a capacity of 20 000 machine hours. During the year, 5100 units were produced. Actual fixed overhead cost $250 000 Actual variable overhead cost $165 750 Actual machine hours worked 19 800 What was Cabinet Maker's fixed overhead budget variance? Select one: a. $5 000 unfavourable b. $2 000 unfavourable c. $7 000 unfavourable d. $4 000 favourable