CABUGERO DEVELOPMENT COMPANY., started work on a construction contract in 2018. The contract price is P10M. However, if the cumulative inflation reaches or exceeds 25%,
CABUGERO DEVELOPMENT COMPANY., started work on a construction contract in 2018. The contract price is P10M. However, if the cumulative inflation reaches or exceeds 25%, the contract price shall be adjusted upward by 10%. Cost escalations on the contract are probable as to recovery. Additional information on the contract is shown below:
2018 2019
Costs incurred to date 2,400,000 4,500,000
Estimated cost at completion 6,000,000 6,000,000
Cumulative inflation rate 18% 27%
1. Compute for the percentage of completion during the year 2018.
2. Compute for the percentage of completion during the year 2019.
3. What is the contract price in 2018?
4. What is the contract price in 2019?
5. What is the realized gross profit in 2018?
6. What is the realized gross profit in 2019?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started