Question: Calculate (ES), (EF), (LS), (LF) times, total float, and free float for each activity. Identify the critical path. ES Act EF LF LS TF

Calculate (ES), (EF), (LS), (LF) times, total float, and free float for

 

Calculate (ES), (EF), (LS), (LF) times, total float, and free float for each activity. Identify the critical path. ES Act EF LF LS TF Dur FF A 2 FS = 0 FS=0 B 3 FF = 3 C FS=0 5 FF = 4 FS=0 SS=2 E FS=0 FS=0 FS=0 5 FS=(-2) FS=(-3) FF = 2 G 4 FF = 1 12 FS=2 FS=0 FS D FS =0 75=0

Step by Step Solution

3.44 Rating (160 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Here are the calculated ES EF LS LF total float and free float for each activity as well as the ... View full answer