Calculate Lead Time Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes:

Calculate Lead Time

Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 80 parts. A part requires 3 minutes in milling and 8 minutes in finishing. The move time between the two operations for a complete batch is 9 minutes.

Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 4 parts and the move time is eliminated.

Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round percentages to one decimal place.

Traditional Philosophy Lean Manufacturing Philosophy
Value-added time fill in the blank 1 min fill in the blank 2 min
Non-value-added time fill in the blank 3 min fill in the blank 4 min
Total lead time fill in the blank 5 min fill in the blank 6 min
Value-added ratio (as a percent) fill in the blank 7 % fill in the blank 8 %

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Theory And Practice

Authors: M. W. E. Glautier, Brian Underdown

7th Edition

0273651617, 978-0273651611

More Books

Students also viewed these Accounting questions

Question

What is involved in the administration of a labor agreement?

Answered: 1 week ago

Question

What are topics included in virtually all labor agreements?

Answered: 1 week ago