Calculate Lead Time Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The

Calculate Lead Time
Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 75 units. The process time for each step is as follows:
Process Step 17 minutes
Process Step 25 minutes
Process Step 34 minutes
Process Step 49 minutes
The time required to move each batch between steps is 14 minutes. In addition, the time to move raw materials to Process Step 1 is also 14 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 14 minutes.
The new lean layout will allow the company to reduce the batch sizes from 75 units to 5 units. The time required to move each batch between steps and the inventory locations will be reduced to 2 minutes. The processing time in each step will stay the same.
Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the present and proposed production approaches. If required, round percentages to one decimal place.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Modern Auditing

Authors: William C. Boynton, Walter G. Kell

6th Edition

0471596876, 9780471596875

More Books

Students also viewed these Accounting questions

Question

How is the tax base of a liability determined?

Answered: 1 week ago

Question

4. Give examples of five potential appraisal problems.

Answered: 1 week ago

Question

6. Explain how to install a performance management program.

Answered: 1 week ago