Calculate Lead TimeFlint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling

CalculateLead TimeFlint Fabricators Inc. machines metal parts for the automotive
industry. Under the traditional manufacturing approach, the parts
are machined through two processes: milling and finishing. Parts
are produced in batch sizes of 85 parts. A part requires 3 minutes
in milling and 7 minutes in finishing. The move time between the
two operations for a complete batch is 8 minutes.Under the lean philosophy, the part is produced in a cell that
includes both the milling and finishing operations. The operating
time is unchanged; however, the batch size is reduced to 5 parts
and the move time is eliminated.Determine thevalue-added,non-value-added, and total
lead times, and thevalue-added ratiounder the
traditional and lean manufacturing methods. If required, round
percentages to one decimal place.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Ray H. Garrison, Eric W. Noreen, Peter C. Brewer

13th Edition

978-0073379616, 73379611, 978-0697789938

More Books

Students also viewed these Accounting questions

Question

=+for the shareholder of the acquiring company?

Answered: 1 week ago

Question

=+for the shareholder of the acquired company?

Answered: 1 week ago

Question

=+for the acquired company?

Answered: 1 week ago