Calculate material, labor, and overhead variances and analyze the results. Item Standard Cost per Unit Actual Cost per Unit Actual Production Direct materials $20 $22

Calculate material, labor, and overhead variances and analyze the results.

Item

Standard Cost per Unit

Actual Cost per Unit

Actual Production

Direct materials

$20

$22

10,000 units

Direct labor

$15

$14

10,000 units

Variable overhead

$10

$11

10,000 units

Fixed overhead

$50,000

$52,000

-

Requirements:

Calculate the material price variance and quantity variance.

Calculate the labor rate variance and efficiency variance.

Calculate the variable overhead spending variance and efficiency variance.

Analyze the overall variance and discuss possible causes.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Information Systems

Authors: Marshall B. Romney, Paul J. Steinbart

12th edition

132552620, 978-0132552622

More Books

Students also viewed these Accounting questions