Calculate the cost-effective order to crash the activities until reaching the minimum duration: Activity A B C D E Predecessors --- --- A B C,D
Calculate the cost-effective order to crash the activities until reaching the minimum duration: Activity A B C D E Predecessors --- --- A B C,D Normal Duration 8 5 4 6 3 Crashed Duration 4 2 2 5 1 Added Cost per crash day 40 60 50 30 20