Calculate the cost-effective order to crash the activities until reaching the minimum duration: Activity A B C D E Predecessors --- A A C B
Calculate the cost-effective order to crash the activities until reaching the minimum duration: Activity A B C D E Predecessors --- A A C B Normal Duration 3 4 6 6 3 Crashed Duration 1 3 2 3 3 Added Cost per crash day 30 20 50 40 60