Question
1 Approved Answer
Calculate the CP for the project and estimate project duration (show your forward and backward calculations for the critical path). Please show the calculations. Activity
Calculate the CP for the project and estimate project duration (show your forward and backward calculations for the critical path). Please show the calculations.
Activity Description Predecessors Duration A City Permit B Bluestake A Layout A Excavation A. B.C Plumbing D F Steel D.E G Electrical F HUNARENASJUNE Inspection Pouring Concrete Finishing Concrete and Pool Tiles K Install Pool Equipment L Install Patio Tiles M Deliver to CustomerActivity Description Predecessors Duration ES EF LS LF Activity Duration A City Permit 0 B Bluestake A 2 3 4 6 2 C Layout A 5 6 1 6 5 D Excavation A, B, C 5 6 11 6 11 5 E Plumbing D 4 11 15 11 15 4 F Steel DE 4 15 19 15 19 4 G Electrical F 2 19 21 19 21 2 H Inspection E, F, G 21 22 21 22 Pouring Concrete H 22 23 22 23 J Finishing Concrete and Pool Tiles 4 23 27 23 27 4 K Install Pool Equipment J 2 27 29 28 30 2 L Install Patio Tiles C 3 27 30 37 30 3 M Deliver to Customer L 30 31 30 311 17 E 11 15 A 1 11 19 G 21 21 27 23 27 5 11 19 2 21 22 73 27 1 14 1 5 27 K L 30 15 4 119 2 30 3 30 Early Activity Early finish = M start=Max of early start + 1 31 early finish of duration last activities Late start= Duration of Late finish= late finish - the activity Min of late duration start of after activitiesStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started