Calculate the EVM formulas for this case. you are the project manager of a project to build wooden kayaks. you are to scheduled build two

Calculate the EVM formulas for this case.
you are the project manager of a project to build wooden kayaks.
you are to scheduled build two kayaks a month for 12 months.
each kayak is budgeted to cost $1000 to build.
your project is scheduled to last for 12 months.
it is the end of month 9.
you have built 20 kayaks and your total cost of labor and materials is $22,000.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Structured Finance Leveraged Buyouts Project Finance Asset Finance And Securitization

Authors: Charles-Henri Larreur

1st Edition

1119371104, 978-1119371106

More Books

Students also viewed these Finance questions