Calculate the following three jobs to be processed on a single machine job pr time Due Date 1 4 2 2 2 3 3 1
Calculate the following three jobs to be processed on a single machine
job pr time Due Date
Enumerate all possible sequences and complete the average cycle time, total tardiness
and maximum lateness for each. Which sequence works best for each measure