Question

1 Approved Answer

calculate the LS and LF of all of the activities please! More Info D. begin{tabular}{ccccc} hline Activity & Duration (weeks) & Predecessors & ES &

calculate the LS and LF of all of the activities please! image text in transcribed
image text in transcribed
image text in transcribed
image text in transcribed
More Info D. \begin{tabular}{ccccc} \hline Activity & Duration (weeks) & Predecessors & ES & EF \\ \hline A & 0.5 & None & 0 & .5 \\ B & 7.5 & None & 0 & 7.5 \\ C & 4 & A, B & 7.5 & 11.5 \\ D & 5.5 & A & 0.5 & 6 \\ E & 3 & C & 11.5 & 14.5 \\ F & 6.5 & D, E & 14.5 & 21 \\ G & 6.5 & F & 21 & 27.5 \\ H & 3.5 & E & 14.5 & 18 \\ \hline \end{tabular} Calcelete Ghe late start and tate finish times for the each activity perfoming the bockward poss. Fil in the thblo below (enter your responsos rounded to one decimer pirce) \begin{tabular}{ccccc} \hline Activity & Duration (woeks) & Predecessors & LS & LF \\ \hlineH & 3.5 & E & & \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these General Management questions