Calculate the NPV of the following project using a discount rate of 12 %. Yr 0 = +RM500; Yr1 = -RM50; Yr2 = RM50; Y3
Calculate the NPV of the following project using a discount rate of 12 %. Yr 0 = +RM500; Yr1 = -RM50; Yr2 = RM50; Y3 = RM200; Yr4 = RM400; Yr5 = RM400 Select one: a. RM208.04 O b. RM 61.22 c. RM 618.75 d. RM118.75