Calculate the NPV of the following project using a discount rate of 10 %: Yr 0 = $ 550; Yr 1 = $ - -60;
Calculate the NPV of the following project using a discount rate of 10 %: Yr 0 = $ 550; Yr 1 = $ - -60; Yr 2 = $45; Yr 3 = $200; Yr 4 = $380; Yr 5 = $440.
Note Yr 0 and Yr 1 Cash flows are negative. Calculate answer to two decimal places.