Question
1 Approved Answer
Calculate the payback period of a project with these cash flows: Period 0: -1000 Period 1: 751 Period 2: 433 Period 3: 250 Enter your
Calculate the payback period of a project with these cash flows:
Period 0: -1000
Period 1: 751
Period 2: 433
Period 3: 250
Enter your answer in years and round to the nearest one-hundredth of a year.
Step by Step Solution
There are 3 Steps involved in it
Step: 1