Question
1 Approved Answer
Calculate the Pay-off Period for an IS project that has a $200,000 development cost in year 1 and annual $40,000 maintenance costs from year 2
- Calculate the Pay-off Period for an IS project that has a $200,000 development cost in year 1 and annual $40,000 maintenance costs from year 2 onwards. The benefits are expected to be $100,000 in Year 2 and growing $25,000 a year as adoption of the system increases. The discount rate is 0%.