Calculate the project cash flow generated for project A and project B using the NPV method. Which project would you select, and why? Which project
Calculate the project cash flow generated for project A and project B using the NPV method. Which project would you select, and why? Which project would you select under the payback method? The discount rate is 10% for both projects. Use Microsoft Excel to prepare your answer. Note that a similar problem is in the textbook in Section 5.1. Sample Template for Project A and Project B