Calculate the running time, using Big-O notation, of the following implementation of the greedy algorithm for the interval scheduling problem. Intreval-Scheduling % R - Array
Calculate the running time, using Big-O notation, of the following implementation of the greedy algorithm for the interval scheduling problem.
Intreval-Scheduling
% R - Array of n requests ;
Sort-by-Finish-Time(R) ;
A <-- {R[0]};
currentReq <-- R[0];
k <-- 1 ;
while k < n do
if currentReq.finishTime <= R[k].startTime then
A <-- A U(union) {R[k]}
currentReq <-- R[k]
end
k++
end