Calculate the takt time for a system where the total time per shift is 480 minutes, there is one shift, and workers are given two
Calculate the takt time for a system where the total time per shift is 480 minutes, there is one shift, and workers are given two 15-minute breaks and 42 minutes for lunch. Daily demand is 315 units
Step by Step Solution
There are 3 Steps involved in it
Step: 1