Calculate the total cost of this job: A manufacturing company is planning to sell a batch of 25 special machines (Job 21) to a retailer
Calculate the total cost of this job: A manufacturing company is planning to sell a batch of 25 special machines (Job 21) to a retailer for $114,800. Direct Materials: $50,000 Direct labor: $19,000 The cost allocation base is machine-hours. Job 21 used 500 machine-hours. 2,480 machine hours were used by all jobs. Manufacturing overhead costs were $65,100. Actual indirect cost rate is ______. Indirect cost allocated to job21 is ______. Total cost of this job is _______.