Calculate the values below: e. Cost performance index f. Schedule performance index g. Budget at completion h. Estimate to complete i. Estimate at completion Status
Calculate the values below:
e. Cost performance index
f. Schedule performance index
g. Budget at completion
h. Estimate to complete
i. Estimate at completion
Status as of Week 9 Task Budget Cost Budget Duration $5,000 1 week A 100 percent com- plete, $4,000 B $8,500 1 week 100 percent com- plete, $8,500 $15,000 2 weeks 100 percent com- plete, $14,000 D $10,000 2 weeks 50 percent com- plete, $9,000 50 percent com- plete, $12,000 E $12,000 3 weeks F $15,000 2 weeks Not started Status as of Week 9 Task Budget Cost Budget Duration $5,000 1 week A 100 percent com- plete, $4,000 B $8,500 1 week 100 percent com- plete, $8,500 $15,000 2 weeks 100 percent com- plete, $14,000 D $10,000 2 weeks 50 percent com- plete, $9,000 50 percent com- plete, $12,000 E $12,000 3 weeks F $15,000 2 weeks Not startedStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started