Question
Calculate the variance analysis for the information provided below using this problem and the formula provided to you. Data: Total payroll cost budgeted: $65,600, actual
Calculate the variance analysis for the information provided below using this problem and the formula provided to you.
Data: Total payroll cost budgeted: $65,600, actual cost: $78,627.5, variance: $13,027.50
Total nursing hours: 1600, actual hours: 1850, variance: 250
Composite Hourly pay rate: $30, actual rate: $33, variance: $3
Patient Days: 350, actual days: 375, Variance: 25
Formulas to use in calculations:
Step #1: Compute the Efficiency Variance.
Budgeted nursing hours / Budgeted patient days = HPPD Budgeted
Actual nursing hours / Actual patient days = HPPD Actual
HPPD Actual - HPPD Budgeted
Actual patient days X extra nursing care hours = Total extra
Total extra X Budgeted hourly wage = Efficiency (in dollars)
Step #2: Compute the volume variance.
Actual patient days - Budgeted patient days = A
A X Budgeted HPPD = B
B X Budgeted pay = V (dollars)
Step #3: Compute the cost variance.
Actual $ paid - Budgeted $ paid = D
D X Actual hours worked = C (dollars)
Step #4: Calculate the Budget Variance.
Efficiency + Volume + Cost = Budget Variance
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started