Calculate the work done and the Earned Value at the end of two weeks in the following situation: Time estimated to complete project: 100 hours
Calculate the work done and the Earned Value at the end of two weeks in the following situation:
- Time estimated to complete project: 100 hours
- Duration of project: 4 weeks
- Planned value: 25 hours per week
- Actual time required over the first two weeks: 40
- Actual time required to finish the project: 30
- Work done = Blank 1%
- Earned value = Blank 2 hours