Calculate the work done and the Earned Value at the end of one week in the following situation: Time estimated to complete project: 60 Duration
Calculate the work done and the Earned Value at the end of one week in the following situation:
- Time estimated to complete project: 60
- Duration of project: 2 weeks
- Planned value: 30 hours per week
- Actual time required over the first week: 40
- Actual time required to finish the project: 45