Calculate the working capital of Daisy under the percentage-of-completion method versus the completed-contract method. Daisy Construction Ltd. has entered into a contract beginning January 1,

Calculate the working capital of Daisy under the percentage-of-completion method versus the completed-contract method.

Daisy Construction Ltd. has entered into a contract beginning January 1, 2014, to build a parking complex. It has estimated that the complex will cost $8 million and will take three years to construct. The complex will be billed to the purchasing company at $11.1 million. The details are as follows:

2014

2015

2016

Costs to date

$

3,060,000

$

6,435,000

$

8,550,000

Estimated costs to complete

4,595,500

1,969,074

0

Progress billings to date

4,000,500

6,300,000

11,100,000

Cash collected to date

3,500,500

5,000,000

11,100,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing Compensation And Benefits Programs

Authors: Kelli W. Vito

1st Edition

0894136720, 978-0894136726

More Books

Students also viewed these Accounting questions

Question

2. Are you varying your pitch (to avoid being monotonous)?

Answered: 1 week ago

Question

3. Are you varying your speaking rate and volume?

Answered: 1 week ago