Calculate total cost per cubic yard of concrete, given the following: Concrete materials and batching costs = $70/cy Trucking = $6.00/cy Paving equipment = $340.00/hr
Calculate total cost per cubic yard of concrete, given the following: Concrete materials and batching costs = $70/cy Trucking = $6.00/cy Paving equipment = $340.00/hr Paving labor = $500.00/hr Paver production = 120 cy/hr Incidentals = $4.00/cy Overhead and profit = 20% of direct costs