Question
CalculateLead Time Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling
CalculateLead Time
Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 45 parts. A part requires 6 minutes in milling and 8 minutes in finishing. The move time between the two operations for a complete batch is 5 minutes.
Under the just-in-time philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 4 parts and the move time is eliminated.
Determine thevalue-added,non-value-added, and total lead times, and thevalue-added ratiounder the traditional and just-in-time manufacturing methods. If required, round percentages to one decimal place.
Traditional Philosophy | Just-in-Time Philosophy | |
Value-added time | min | min |
Non-value-added time | min | min |
Total lead time | min | min |
Value-added ratio (as a percent) | % | % |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started