CalculateLead Time Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production
CalculateLead Time
Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 63 units. Theprocesstime for each step is as follows:
Process Step 17minutesProcess Step 25minutesProcess Step 34minutesProcess Step 49minutes
The time required to move each batch between steps is 17 minutes. In addition, the time to move raw materials to Process Step 1 is also 17 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 17 minutes.
The new lean layout will allow the company to reduce the batch sizes from 63 units to 4 units. The time required to move each batch between steps and the inventory locations will be reduced to 3 minutes. The processing time in each step will stay the same.
Determine thevalue-added,non-value-added, and total lead times, and thevalue-added ratiounder the present and proposed production approaches. If required, round percentages to one decimal place.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started