Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following activities and costs: Setup (1,000 setup hours) $118,000 Production
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following activities and costs:
Setup (1,000 setup hours) | $118,000 |
Production scheduling (400 batches) | 60,000 |
Production engineering (60 change orders) | 150,000 |
Supervision (2,000 direct labor hours) | 46,000 |
Machine maintenance (12,000 machine hours) | 60,000 |
Total activity costs | $434,000 |
The following additional data were provided for Job 845:
Direct materials costs | $7,000 |
Direct labor cost (5 Milling direct labor hours;35 Finishing direct labor hours) | $1,000 |
Setup hours | 5 hours |
Production scheduling | 1 batch |
Machine hours used (25 Milling machine hours;5 Finishing machine hours) | 30 hours |
Production engineering | 3 change orders |
(a) Calculate the cost per unit of activity driver for each activity cost category. Setup $Answer Production scheduling $Answer Production engineering $Answer Supervision $Answer Machine maintenance $Answer (b) Calculate the cost of Job 845 using ABC to assign the overhead costs. $Answer (c) Calculate the cost of Job 845 using the plantwide overhead rate based on machine hours. (Round your answer to the nearest dollar.) $Answer (d) Calculate the cost of Job 845 using a machine hour departmental overhead rate for the Milling Department ($32 per hour) and a direct hour overhead rate for the Finishing Department ($102 per hour). (Round your answer to the nearest dollar.) $Answer
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started