CALCULATOR PRINTER VERSION BACK NEXT Exercise 16-11 (Part Level Submission) The Polishing Department of Major Company has the following production and manufacturing cost data for September. Materials are entered at the beginning of the process. Production: Beginning inventory 1,720 units that are 100% complete as to materials and 30% complete as to conversion costs; units started during the period are 40,000; ending inventory of 5,200 units 10% complete as to conversion costs. Manufacturing costs: Beginning inventory costs, comprised of $20,200 of materials and $12,029 of conversion costs; materials costs added in Polishing during the month, $172,964; labor and overhead applied in Polishing during the month, $127,100 and $257,940, respectively. Your answer is correct Compute the equivalent units of production for materials and conversion costs for the month of September. Materials Conversion Costs The equivalent units of production 41720 37040 Click if you would like to Show Work for this question: Open Show Work SHOW SOLUTION SHOW ANSWER LINK TO TEXT VIDEO: APPLIED SKILLS Attempts: 1 of 3 used (b) Your answer is correct. Compute the unit costs for materials and conversion costs for the month. (Round unit costs to 2 decimal places, eg, 2.25.) Materials Conversion Costs Unit costs 4.63 10.72 Click if you would like to show Work for this question: Open Show Work SHOW SOLUTION SHOW ANSWER CALCULATOR PRINTER VERSION BACK NEXT LINK TO TEXT VIDEO: APPLIED SKILLS Attempts: 1 of 3 used (b) Your answer is correct. Compute the unit costs for materials and conversion costs for the month. (Round unit costs to 2 decimal places, e.g. 2.25.) Materials Conversion Costs Unit costs 4.63 10.72 Click if you would like to show Work for this question: Open Show Work SHOW SOLUTION SHOW ANSWER LINK TO TEXT VIDEO APPLIED SKILLS Attempts: 1 of 3 used Determine the costs to be assigned to the units transferred out and in process. (Round unit costs to 2 decimal places, e.g. 2.25 and final answers to decimal places, e.g. 1,225.) Transferred out Ending work in process Click if you would like to show Work for this question: Modify Show Work