Can someone please help me with this question. I'll upvote for a fast response. Please show the working out so I can understand. Deron Construction

Can someone please help me with this question. I'll upvote for a fast response.

Please show the working out so I can understand.

image text in transcribed
Deron Construction Limited currently has two construction contracts. The contracts involve the construction of a Clinic at Grange hill, Westmoreland and a new hotel in Negril. Management is unaware with regard to when revenue, costs and profits from the contracts are to be recognized. Based on the construction industry as well as the entity's accounting policies, the outcome of a contract cannot be estimated reliably until a contract is at least 15% complete. Below are information relating to both contracts for the year ended December 31, 2020 Clinic Hotel Contract Price $25,000,000 $100,000,000 Cost Incurred to date $5,000,000 $7,500,000 Estimated cost to complete $7,500,000 $67,500,000 Progress Billing S6,000,000 $2,500,000 Cash received $4,500,000 $2.000.000 The company uses the input method to determine the projects' level of completion. The company recognised revenues and cost on the clinic amounting to $1,500,000 and $1,750,000 for the year ended December 31, 2019. Management indicates that contract costs incurred are probable of being recovered Required: a) Prepare an extract of the statement of profits or loss to recognize contract revenue, cost and profits for the year ended December 31, 2020 b) Prepare an extract of the statement of financial position as at December 31, 2020 Deron Construction Limited currently has two construction contracts. The contracts involve the construction of a Clinic at Grange hill, Westmoreland and a new hotel in Negril. Management is unaware with regard to when revenue, costs and profits from the contracts are to be recognized. Based on the construction industry as well as the entity's accounting policies, the outcome of a contract cannot be estimated reliably until a contract is at least 15% complete. Below are information relating to both contracts for the year ended December 31, 2020 Clinic Hotel Contract Price $25,000,000 $100,000,000 Cost Incurred to date $5,000,000 $7,500,000 Estimated cost to complete $7,500,000 $67,500,000 Progress Billing S6,000,000 $2,500,000 Cash received $4,500,000 $2.000.000 The company uses the input method to determine the projects' level of completion. The company recognised revenues and cost on the clinic amounting to $1,500,000 and $1,750,000 for the year ended December 31, 2019. Management indicates that contract costs incurred are probable of being recovered Required: a) Prepare an extract of the statement of profits or loss to recognize contract revenue, cost and profits for the year ended December 31, 2020 b) Prepare an extract of the statement of financial position as at December 31, 2020

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting

Authors: Carl S. Warren, James M. Reeve, Philip E. Fess

20th Edition

0324025424, 978-0324025422

More Books

Students also viewed these Accounting questions

Question

Show enthusiasm for the position (but not too much).

Answered: 1 week ago