Can you develop a network diagram with the table given below?
Nr | Main Activities with Predecessors | ||||||||
Name of the tasked | Duration | Predecessors | Start | Finish | EST | EFT | LST | LFT | |
1 | Budget approval | 1 day | - | 1/11/2023 | 1/11/2023 | 1/11/2023 | 1/11/2023 | 1/11/2023 | 1/11/2023 |
2 | Hire publicity team | 14 days | 1 | 1/11/ 2023 | 16/11/2023 | 1/11/ 2023 | 16/11/2023 | 1/11/ 2023 | 16/11/2023 |
3 | Hire course/event designer | 14 days | 1 | 16/11/2023 | 05/12/2023 | 16/11/2023 | 05/12/2023 | 16/11/2023 | 05/12/2023 |
4 | Hire event location | 7 days | 2 | 05/12/2023 | 13/12/2023 | 05/12/2023 | 13/12/2023 | 05/12/2023 | 13/12/2023 |
5 | Advertising to higher event crew | 7 days | 4 | 05/12/2023 | 13/12/2023 | 05/12/2023 | 13/12/2023 | 05/12/2023 | 13/12/2023 |
6 | Hire event crew | 28 days | 5 | 14/12/2023 | 11/01/2024 | 14/12/2023 | 11/01/2024 | 14/12/2023 | 11/01/2024 |
7 | Event designed | 42 days | 3, 6 | 14/12/2023 | 25/01/2024 | 14/12/2023 | 25/01/2024 | 14/12/2023 | 25/01/2024 |
8 | Train event crew | 12 days | 3, 6 | 14-12- 2023 | 25-12-2023 | 14-12- 2023 | 25-12-2023 | 26/01/2024 | 6/2/2024 |
9 | Advertise charity event & set up website | 5 days | 2, 4, 6 | 26/01/2024 | 31/01/2024 | 26/01/2024 | 31/01/2024 | 7/01/2024 | 12/02/2024 |
10 | Get public to sign up for event | 84 days | 9 | 24-10- 2023 | 20-12- 2023 | 24-10- 2023 | 20-12- 2023 | 13/02/2024 | 6/4/2024 |
11 | Sign up guest celebrities to be at event | 7 days | 2, 4 | 24-10-2023 | 08-11-2023 | 24-10-2023 | 08-11-2023 | 7/4/2024 | 14/4/2024 |
12 | Event design sign off | 2 days | 7 | 24/10/2023 | 26/10/2023 | 24/10/2023 | 26/10/2023 | 15/4/2024 | 17/4/2024 |
13 | Photograph celebrities and crew & collect biographies | 35 days | 11 | 24/10/2023 | 11/12/2023 | 24/10/2023 | 11/12/2023 | 18/4/2024 | 21/6/2024 |
14 | Enter information into computer | 1 day | 13 | 12/12/2023 | 12/12/2023 | 12/12/2023 | 12/12/2023 | 22/6/2024 | 22/6/2024 |
15 | printing | 5 days | 14 | 13/12/2023 | 18/12/2023 | 13/12/2023 | 18/12/2023 | 25/6/2024 | 30/6/2024 |
16 | Develop an advertising plan | 7 days | 4, 11 | 19/12/2023 | 26/12/2023 | 19/12/2023 | 26/12/2023 | 1/7/2-24 | 7/7/2024 |
17 | Advertising media | 21 days | 16 | 26/12/2023 | 16/01/2024 | 26/12/2023 | 16/01/2024 | 8/7/2024 | 29/7/2024 |
18 | Event built | 5 days | 12 | 17/01/2024 | 22/01/2024 | 17/01/2024 | 22/01/2024 | 30/7/2024 | 4/8/2024 |
19 | Purchase crew uniform | 7 days | 6 | 22/01/2024 | 27/01/2024 | 22/01/2024 | 27/01/2024 | 5/8/2024 | 12/8/2024 |
20 | Final event design alterations | 5 days | 7, 18 | 27/01/2024 | 1/02/2024 | 27/01/2024 | 1/02/2024 | 13/8/2024 | 18/8/2024 |
21 | Event rehearsal | 1 day | 8, 11, 18, 20 | 02/02/2024 | 03/02/2024 | 02/02/2024 | 03/02/2024 | 19/8/2024 | 19/8/2024 |
22 | Event | 2 days | 15, 17, 21 | 04/02/2024 | 06/02/2024 | 04/02/2024 | 06/02/2024 | 20/8/2024 | 22/8/2024 |