can you provide calculations and step-by-step solutions? can you also use table format wherever required? A project has the following information (FS dependencies). o What

can you provide calculations and step-by-step solutions? can you also use table format wherever required?

image text in transcribed
A project has the following information (FS dependencies). o What is the duration of the critical path? (5 marks) (Hint: you do not need to do a forward and backward pass) . What is the probability in completing the project between '13 and 21 time periods? (15 Marks) Optimistic Most Likely Pessimistic Predecessors 3 ............. 5 3 4 A 2. ,, ,, 3 ,, A 3 5 B 4 7 B 2. C 4 E,F 3 D 2. G,H

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Exploring The Hospitality Industry

Authors: John R Walker, Josielyn T Walker

3rd Edition

0133762777, 9780133762778

More Books

Students also viewed these General Management questions