Can you solve this problem and give a calculation process? Thanks! Exercise 6-20 (Algo) Long-term contract; revenue recognition over time vs. upon project completion [LO6-9]

Can you solve this problem and give a calculation process? Thanks!

image text in transcribedimage text in transcribedimage text in transcribedimage text in transcribed

Exercise 6-20 (Algo) Long-term contract; revenue recognition over time vs. upon project completion [LO6-9] On June 15, 2024, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $400 million. The expected completion date is April 1, 2026, just in time for the 2026 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows (\$ in millions): 1. Compute the revenue and gross profit that Sanderson will report in its 2024,2025 , and 2026 income statements related to this contract, assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit that Sanderson will report in its 2024,2025 , and 2026 income statements related to this contract, assuming this project does not qualify for revenue recognition over time. 3. Suppose the estimated costs to complete at the end of 2025 are $150 million instead of $50 million. Compute the amount of revenue and gross profit or loss to be recognized in 2025 , assuming Sanderson recognizes revenue over time according to percentage of completion. Compute the revenue and gross profit that Sanderson will report in its 2024,2025 , and 2026 income statements related to this contract, assuming Sanderson recognizes revenue over time according to percentage of completion. Note: Enter your answer in millions (i.e., $4,000,000 should be entered as $4 ). Loss amounts should be indicated with a minus sign. Use percentages as calculated and rounded in the table below to arrive at your final answer. Compute the revenue and gross profit that Sanderson will report in its 2024,2025 , and 2026 income statements related to this contract, assuming this project does not qualify for revenue recognition over time. Note: Enter your answer in millions (i.e., $4,000,000 should be entered as $4 ). Loss amounts should be indicated with a minus sign. Leave no cells blank. Suppose the estimated costs to complete at the end of 2025 are $150 million instead of $50 million. Compute the amount of revenue completion. table below to arrive at your final answer. Loss amounts should be indicated with a minus sign

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

International Fraud Handbook

Authors: Joseph T. Wells

1st Edition

1118728505, 9781118728505

More Books

Students also viewed these Accounting questions