Canyouhelpme with this questionYou are managing a project to expand a major county road in your area. The project is expected to take 1 year
Canyouhelpme with this questionYou are managing a project to expand a major county road in your area. The project is expected to take 1 year and the expenses are budgeted to be $12,500 per month. Six months after the project started, you find out that the project is 50% complete, and that you have spent $70,000. Fill in the information in the table below:
Item | Value |
BAC | |
PV | |
EV | |
AC | |
CV = EV-AC | |
SV = EV PV | |
CPI = EV/AC | |
SPI = EV/PV | |
EAC = BAC/CPI | |
ETC = EAC-AC | |
VAC = BAC-EAC | |
TCPI (Cost) = (BAC-EV)/(BAC-AC) |
Based on the values you computed, is the project ahead of schedule or behind schedule? Will the project be completed under budget or will it exceed the budget?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started