Capacity: Which of the following are levers to increasing theoretical capacity of a process? Increase the unit load on a bottleneck resource Increase the number
Capacity: Which of the following are levers to increasing theoretical capacity of a process? Increase the unit load on a bottleneck resource Increase the number of bottleneck resources Decrease the unit load on a bottleneck resource Increase the batch size at a bottleneck resouce Increase the scheduled availability of the bottleneck resource Decrease the batch size at a bottleneck resouce Decrease the scheduled availability of the bottleneck resource