Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Cardiff and Delp is an architectural firm that provides services for residential construction projects. The following data pertain to a recent reporting period. Activities Costs
Cardiff and Delp is an architectural firm that provides services for residential construction projects. The following data pertain to a recent reporting period.
Activities | Costs | ||||
Design department | |||||
Client consultation | 1,800 | contact hours | $ | 270,000 | |
Drawings | 2,400 | design hours | 130,800 | ||
Modeling | 47,000 | square feet | 30,550 | ||
Project management department | |||||
Supervision | 1,200 | days | $ | 216,000 | |
Billings | 8 | jobs | 8,700 | ||
Collections | 8 | jobs | 11,780 | ||
1. & 2. Using ABC, compute the firm's activity overhead rates. Form activity cost pools where appropriate. Assign costs to a 6,800-square-foot job that requires 460 contact hours, 342 design hours, and 165 days to complete. (Round activity rate answers to 2 decimal places.)
Activity Expected Costs Expected Activity Driver Activity Rate Activity Driver Incurred Overhead Assigned Client consultation 0 Drawings Modeling Supervision Billings/Collection 0 0 Total overhead cost
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started