carrying cost is $ 1 0 . 4 0 per motor. It currently takes 2 weeks to supply an order to the assembly plant. Read

carrying cost is $10.40 per motor. It currently takes 2 weeks to supply an order to the assembly plant.
Read the requirements.
Requirement 1. What is the optimal number of motors that Harris's managers should order according to the EOQ model?
Begin by selecting the formula used to calculate EOQ. Demand in units for one year, P= Ordering cost per purchase order, C= Carrying cost of one unit in stock, Q= Any order quantity)
EOQ=2DPC2
The optimal number of motors per order is
motors.
Requirements
What is the optimal number of motors that Harris' managers should order
according to the EOQ model?
At what point should managers reorder the motors, assuming that both demand
and purchase-order lead time are known with certainty?
Now assume that demand can vary during the 2-week purchase-order lead time.
The following table shows the probability distribution of various demand levels:
If Harris runs out of stock, it would have to rush order the motors at an additional
cost of $3 per motor. How much safety stock should the assembly plant hold? How
will this affect the reorder point and reorder quantity?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Customer Support Audit

Authors: Colin G. Armistead

1st Edition

190776609X, 978-1907766091

More Books

Students also viewed these Accounting questions

Question

How does selection differ from recruitment ?

Answered: 1 week ago