Question
1 Approved Answer
carrying cost is $ 1 0 . 4 0 per motor. It currently takes 2 weeks to supply an order to the assembly plant. Read
carrying cost is $ per motor. It currently takes weeks to supply an order to the assembly plant.
Read the requirements.
Requirement What is the optimal number of motors that Harris's managers should order according to the EOQ model?
Begin by selecting the formula used to calculate EOQ. Demand in units for one year, Ordering cost per purchase order, Carrying cost of one unit in stock, Any order quantity
EOQ
The optimal number of motors per order is
motors.
Requirements
What is the optimal number of motors that Harris' managers should order
according to the EOQ model?
At what point should managers reorder the motors, assuming that both demand
and purchaseorder lead time are known with certainty?
Now assume that demand can vary during the week purchaseorder lead time.
The following table shows the probability distribution of various demand levels:
If Harris runs out of stock, it would have to rush order the motors at an additional
cost of $ per motor. How much safety stock should the assembly plant hold? How
will this affect the reorder point and reorder quantity?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started